shadestreet
Technical User
Can anyone recommend a good site with tutorials on using Microsoft Project?
Also, I have a Gantt chart created and I wanted to add "% Work Complete" column, but I want to manually over-ride the percentages without the dates being changed. Through the Options>>Calculations tab I unchecked some fields that allow me to over-ride the percent of work complete, but I cannot modify the parent task. For example:
I have a group where the three pieces to the main function are all at 100%, but the parent row for the group will not change from 0% no matter what I do.
Thanks
Also, I have a Gantt chart created and I wanted to add "% Work Complete" column, but I want to manually over-ride the percentages without the dates being changed. Through the Options>>Calculations tab I unchecked some fields that allow me to over-ride the percent of work complete, but I cannot modify the parent task. For example:
I have a group where the three pieces to the main function are all at 100%, but the parent row for the group will not change from 0% no matter what I do.
Thanks