Greetings
I selected "Hold Schedule" on a job that just started running because it was suspected of causing problems. Now the job still shows as running, a week later, but is not doing anything and did not run on it's next scheduled time which was last night. Other scheduled jobs have ran sucsessfully in between.
How can I undo this so it goes back to being "Scheduled" Right click and trying remove the hold does nothing
Thanks
Kenny
I selected "Hold Schedule" on a job that just started running because it was suspected of causing problems. Now the job still shows as running, a week later, but is not doing anything and did not run on it's next scheduled time which was last night. Other scheduled jobs have ran sucsessfully in between.
How can I undo this so it goes back to being "Scheduled" Right click and trying remove the hold does nothing
Thanks
Kenny