MS Project noob here, so please be patient over the next couple of weeks!
MS Project 2003.
2 x team members that I want to initially assign to 'general' duties for a full 12 month period, 5 days per week, 48 weeks per year.
So; first pass - they both have 1 task apiece for 12 months.
This task is basically a 'catch-all' task - if they aren't given specific tasks - then they are shown as performing this general task.
As time goes on, they will be assigned additional 'specific' tasks - varying lengths of time - as and when.
When I add a specific task and assign one of these 'resources' to it and then level - I'd like it to remove their entry from their 'general' task for the period of the specific task (without squawking about this resource being 'over-allocated').
(The only tasks worth reporting-on are the specific ones, but I feel that the 'general' task bar will highlight the fact that we aren't specifying / categorising tasks well enough.)
Am I going about this in a completely incorrect way? If not - can anyone point me toward what I need to be setting to enable this?
Thanks for any help.
Darrylles
Never argue with an idiot, he'll bring you down to his level - then beat you with experience.
MS Project 2003.
2 x team members that I want to initially assign to 'general' duties for a full 12 month period, 5 days per week, 48 weeks per year.
So; first pass - they both have 1 task apiece for 12 months.
This task is basically a 'catch-all' task - if they aren't given specific tasks - then they are shown as performing this general task.
As time goes on, they will be assigned additional 'specific' tasks - varying lengths of time - as and when.
When I add a specific task and assign one of these 'resources' to it and then level - I'd like it to remove their entry from their 'general' task for the period of the specific task (without squawking about this resource being 'over-allocated').
(The only tasks worth reporting-on are the specific ones, but I feel that the 'general' task bar will highlight the fact that we aren't specifying / categorising tasks well enough.)
Am I going about this in a completely incorrect way? If not - can anyone point me toward what I need to be setting to enable this?
Thanks for any help.
Darrylles
Never argue with an idiot, he'll bring you down to his level - then beat you with experience.