itchyII
MIS
- Apr 10, 2001
- 167
Hi Everyone,
I have a project 2000 file with my projects and tasks are assigned to resources. I am using fixed work, therefore I have hours assigned to tasks and the duration can vary allowing for proper resource allocation. My problem is this. If I have a task that was set to 8 hours over 4 days, my resource has been allocated at 25%. Before the start date of the task, this is fine. If on the first day, the resource does not do any work on the task, I would like the 8 hours to show up redistributed over the balance of the days on the resource graph. So instead of showing 25% allocation for this task on days 2,3 & 4, I want it to now show 33% for those days. Is this possible?
Thanks in advance!
ItchyII
I have a project 2000 file with my projects and tasks are assigned to resources. I am using fixed work, therefore I have hours assigned to tasks and the duration can vary allowing for proper resource allocation. My problem is this. If I have a task that was set to 8 hours over 4 days, my resource has been allocated at 25%. Before the start date of the task, this is fine. If on the first day, the resource does not do any work on the task, I would like the 8 hours to show up redistributed over the balance of the days on the resource graph. So instead of showing 25% allocation for this task on days 2,3 & 4, I want it to now show 33% for those days. Is this possible?
Thanks in advance!
ItchyII