Hi: My question is about resource leveling (assigning tasks to a machine).
I have 3 machines - all identical. All run 24 hours/day. I also have about 10 tasks (each independent of other). Each task can be done by any of the 3 machines. (The duration of each task is different, though. Some require 10 days, others require 3 days, etc.)
I want MS Project (version 2003) to do the leveling for me. I want it to pick one of the 3 machines to one task, and then another machine to second task etc. It should do the "machine leveling" for me, meaning it can put tasks in such order that machines are fully "occupied".
IS THIS POSSIBLE? IF SO, HOW?
I have 3 machines - all identical. All run 24 hours/day. I also have about 10 tasks (each independent of other). Each task can be done by any of the 3 machines. (The duration of each task is different, though. Some require 10 days, others require 3 days, etc.)
I want MS Project (version 2003) to do the leveling for me. I want it to pick one of the 3 machines to one task, and then another machine to second task etc. It should do the "machine leveling" for me, meaning it can put tasks in such order that machines are fully "occupied".
IS THIS POSSIBLE? IF SO, HOW?