ShipConsulting
Technical User
I am attempting to assign resources to various tasks. To avoid overallocating a resource (in this case welders) I want welder 1 to start welding on 3/13, then when Welder 2 becomes available I want to assign him to start on this same task that welder 1 is working but not until 3/16, and so on as my welders become free. I am running into this allocation issue across my entire project and cannot find a way to assign resources in a cascading fashion. Any specific answers are welcomed, thanks.