davidd31415
Programmer
My "current date" is set to 2/14/06 in project.
When I change a task to start "as soon as possible" the start date changes to 1/10/06.
How can I tell project that I would like a task started "as soon as possible" but not "before today" ?
When I change a task to start "as soon as possible" the start date changes to 1/10/06.
How can I tell project that I would like a task started "as soon as possible" but not "before today" ?