MW
When the user enters a new task from the browser the task appears correctly in the Timesheet of the resource and in the project.

But:

How can I make tasks of an already existing project appear in the timesheet of a resource in project central???

 
To make exsisting tasks show in the PC timesheet, you will need to have the task assigned to a resourse, and then update the PC server by "resend all messages" from within Project 2000.

-Tyler Lynch
 