Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations IamaSherpa on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Adjusting task timeline w/o having resource hours change

Status
Not open for further replies.

davem1717

Technical User
May 5, 2004
1
US
We have lump sum projects that we track in MS Project. The tasks, budgeted hours by resource, and duration are initially inputed. During the life of some projects the time line is adjusted which also automatically adjusts the hours. Is there anyway to lock the budget hours so that the hours do not adjust when the time duration is altered?

Thanks

Dave
 
What's the problem with making them Fixed Work tasks?
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top