The project I am on is 24/7 with two 12-hour shifts. The morning shift is 7AM to 7PM, night shift is 7PM to 7AM. I have adjusted the Timescale by Tier 1: Day (count 1) and Tier 2: Hour (count 4). I have set the Project to 24-hour with no non-workperiods.
Now, what I need, is the day to start at 7AM. Right now, for example, I look at Tier 1 and it says Mar. 28 and Tier 2 says 12, 6, 12, 6. What I want is Tier 1 to say Mar. 28 and Tier 2 to say 7, 1, 7, 1. Can I make this happen? How?
Now, what I need, is the day to start at 7AM. Right now, for example, I look at Tier 1 and it says Mar. 28 and Tier 2 says 12, 6, 12, 6. What I want is Tier 1 to say Mar. 28 and Tier 2 to say 7, 1, 7, 1. Can I make this happen? How?