Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Mike Lewis on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Adding text to the milestone bar

Status
Not open for further replies.

SloopJohnB1

Technical User
Jun 18, 2009
8
NZ
Can I add task name to the milestone bar to the left as the date is automatically placed to the right.

I have set up a column "Text 1" and copied the task names into it and have set the bar text up to display Text 1 to the right. Now I have made a second column "Text 2" but I can not get it to display to the left of the milestone.
 
Hi,

I am not able to reproduce this issue. Are you using Format > Bar or Format > Bar Styles?

Using Project 2010, Format > Bar Styles and placing Text1 to the left and Text2 to the right works fine.

What version of Project are you using?

Julie
 
Hi,

I've downloaded your file, used Format > Bar Styles, selected the milestone bar style and elected to show Text2 to the left and Finish date to the right. It appears without trouble.

Saved, closed, re-opened the file and all was well.

What service pack do you have applied? You should be at SP-3 for Project 2007.

Julie
 
Thank you for your help, that is some else I have learnt about Project, that each bar style is changeable.

Running SP2 will update.
 
Status