I want to track progress on a project by
1) actual work (hours)
2) actual finish
but the two are linked somehow. I want to track each independently.
For example, I spend 2 hours a day for four days on a task, and so I enter 8 hours as actual work. But then it tries to tell me that I've spent it all in one day. I want my GANTT to show that I spent 8 hours on the task and finished it 4 days after the start date.
Thanks.