Can anyone help me with an issue I am having? We produce large enclosures at my place of work. These enclosures undergo several revisions in process. When this happens our actively scheduled jobs lose their resources. I am looking for help with a BAQ to indicate to me which schedules by operation I need to look at to reassign resources. At present we are having to use nearly 2 hours daily to correct this issue. A report to tell us where to focus our efforts would be a huge step in the right direction.