Hi there,
I'm hoping you guys can help me with a very confusing problem I am having with one of my resources. I have this resource assigned to a 3 month long task, in which she only needs to work 8 hours. The program divides her time up and she's working less than half an hour a day.
But project is saying she's over allocated the whole time!
I've made sure she's on a schedule just like everyone else I have, doesn't seem to matter, still red warnings everywhere. I even tried just deleting the resource and recreating it. I don't understand why every other resource I've assigned to the task works fine, it's just this one that is a problem.
The other funny thing about it is if I go into levelling options and set it to a week by week option, it resolves the problem, but I don't want it set to week by week.
Anyone have any ideas as to what might be happening?
I'm hoping you guys can help me with a very confusing problem I am having with one of my resources. I have this resource assigned to a 3 month long task, in which she only needs to work 8 hours. The program divides her time up and she's working less than half an hour a day.
But project is saying she's over allocated the whole time!
I've made sure she's on a schedule just like everyone else I have, doesn't seem to matter, still red warnings everywhere. I even tried just deleting the resource and recreating it. I don't understand why every other resource I've assigned to the task works fine, it's just this one that is a problem.
The other funny thing about it is if I go into levelling options and set it to a week by week option, it resolves the problem, but I don't want it set to week by week.
Anyone have any ideas as to what might be happening?