    Why is edays (leveling delay) being factored when i save a baseline

    hmm. this may be a 2003 srv sp1 vs 2003 clnt non-sp1 issue. or maybe just my client. the problem does not appear to be appearing on another box, so maybe this is not actually an issue?
  2. cfeig

    Why is edays (leveling delay) being factored when i save a baseline

    update: doing the above along with splitting seems to allow me to solve the problem. make sense?
  3. cfeig

    Why is edays (leveling delay) being factored when i save a baseline

    i think i may have found a solution. Using resource allocation view and adjusting "assignment delay" along with duration (with fixed work task types) allows me to resolve my resource allocation issues. then i can still baseline. does this sound right?
  4. cfeig

    Why is edays (leveling delay) being factored when i save a baseline

    here is a description of this problem i found on google groups which matches my situation... has anyone found a solution to this? In short, if i manually enter leveling delay or let project do leveling, and then i baseline, the baseline copies the right start date, but then changes the current...