For most of my MS Projects (2003) I load the task duration in days but want to really show total hours per task per day especially if there are other projects.
i.e.
A 6 hour task that takes 3 days (2hrs of resource per day)
If I say 6 hours MS Project assumes 8 hrs per day. I cant reset...