I need to have tasks that have a duration that exceeds the work of the resource assigned eg task duration is 5 days, resource effort is 2 man days.
I would like MSP to front-load the resource ie in the example above the two man days would occur on days 1 and 2 of the 5-day task.
If I use fixed...