thanks info. Reason I want to do this is to analyse total number of "man-days of work" it takes for a project to complete.
For example:-
If Task One takes 2 days, Task Two takes 5 days and Task Three takes 7 days, the Duration is 7 days but the total time to do all three is 14 days. Each Task...
Can anyone tell me how to (easily) set up a column in MS Project 2003 that enables me to see the total or cumulatative time spent on a project containing various independant tasks?
For example,for three tasks not dependant on each other, if Task One takes 2 days, Task Two takes 5 days and Task...