Hi,
I'm a fairly new MS Project user and in need of some help tuning the Duration column. I have two staff, A and B; A works 2 hours a day and B works 1 hour a day. I have set the "Hours per day" to 2 hours.
Now this works for A who's hours are the same as Hours per day. However, let say I...