I have a project plan on which i have created several views that allow me to pull the different functional areas (items we are delivering) into separate views, reports etc.
Note: These functional areas are spreadout throughout the entire plan.
What i would like to do is be able to get a...
hi there,
I've tried to do the same also and have found that you cannot change the source of the calculation for the "% Complete" field. I just had to work round it by creating a custom number field that worked the calculation for me and then transfer the resultant number to the %...