Hi
Imagine there were several more countries in the example posted. I want line 20 to look at 5,11,17 and tell me the which line happened first.
thankshttp://files.engineering.com/getfile.aspx?folder=daba00a1-392e-4ff5-831c-8e1471d5e830&file=Capture.JPG
Hi, first-time caller,
in MS Project 16 I have several tasks repeating themselves in groups of subtask. ie several countries but each country have the same tasks and each country is running in parallel to other countries. My question is, I want to be able to see the date, the earliest or latest...