Hello:
I a trying to figure out a way(best way) to determine a "planned % complete" simply based on the number of days in a task.
For example:
Task Start Date = 3/1/15
Task Finish Date = 3/20/15
So the task is 20 days long
Today is 3/10/15 so "planned % complete" should be 50%
(Today-Start) /...