Julie,
Thanks very much for your thorough response - it is appreciated.
To close this one out I have a further question (which I'm presuming will expose another limitation in MS Project).
To get around what you've previously mentioned with resource over allocation, I'm trying to allocate...
Hi
Just realised that the resource table hasn't uploaded correctly.
I've now attached this.
Please see below
Thanks
Derekhttp://files.engineering.com/getfile.aspx?folder=2f3b3e6c-0ebc-4c95-b11f-8ed04b69b0fc&file=Ms_Project_-_Forum_issue.docx
Hi,
I have a query regarding MS Project’s ability to enable auto-resource levelling and in particular, allocation of a resource at over 100% capacity.
To be clear, I am using MS Project 2010 and not MS Project Server.
The background to my issue is:
1. I work on a large IT project and need to...