First, thanks to all who responded. Since posting I did a bit more work.
I created a new calendar 8 hour days 7 work days per week. The calculation showed the dates as expected. But it only calculates 40 hours/week not the 168 hours it actually is.
In this case it doesn't matter because the...
I am having a problem calculating dates/durations.
For most of the project, I am using the standard calendar (with company holidays added).
One task is a process that will run 24 hours 7 days a week. I created a task to start on 8/21/14 with a duration of 114 days.
The standard calendar...