Well ... I found the culprit ...
Some of the tasks were marked as manually scheduled tasks. In one case a high-level summary task was created this way and all tasks affected were within that summary task. Once I changed it to automatic, this problem went away.
Todd
Hi -
I'm new to this forum, I hope someone can help.
I am working with a schedule recently built in MSP 2013 that has many >zero slack tasks showing as critical. This is my first time using MSP 2013 (I am an advanced user on earlier versions).
I've analyzed the settings for the usual...