I will try to simplify my question:
Each Task must have two resources. One resource Type 1 and one resource Type 2. I enter resource type 1 manually, but i wish ms project would assign resource type 2 automatically.
Combination Constraints:
Resource Type 1 | Resource Type 2
R1...
Hello,
I'm trying to use MS Project for production planning. I know it is not the right tool to do it, but i still want to give it a try.
I have several machines (RT1: Resource type 1) and several structures (RT2: Resource type 2). The structures (RT1) are puted physically inside the machines...