Ok Thanks, sorry I worded that wrong. I assign the initial resource that the task is assigned to. I was wondering if there was a way to get projects to assign more than 100% of that resource to a task once I already determined which resource was assigned to the task in the first place.
From...
I am having a problem allocating resources from a pool of technicians. Here is what I'm trying to do.
I currently have several groups of resources (Welders, Pipe Fitters, etc..) I've set up their max units to be >100% according to how many people are in each shop (300%=3 people etc..).
When I...