  1. Dazzah666

    Best way to move a task deadline without constraining it

    Thanks that has sorted it, I basically created a large exception in the calendar until the supplier start date, it's interesting to know that if you stagger available work by date it has a similar affect as applying a back loaded contour
  2. Dazzah666

    Best way to move a task deadline without constraining it

    Apologies, In my haste I poorly worded the thread title, it meant to read Best way to move a task start date without constraining it
  3. Dazzah666

    Best way to move a task deadline without constraining it

    Hi, I've been informed by a contractor of a particular date that they are able to commence work for us. They will be doing work throughout the project but will be unable to begin until later next month. I want the tasks in MS project to reflect that but I do not want to constrain the individual...