Julie, that is consistent with what I have found but what I would like to do is have a task that has fixed work of say 40 hours, with "worker 1" assigned to the task, and a work location of "lab" assigned to the task. When I try to do this using work resources for both the worker and the work...
I am somewhat new to MS project and have been stumbling through several issue but I have not been able to figure out how to add in a Resource like a work cell or production area to a task so that I can avoid double booking the resource location. I want to add this as a resource so I can then use...