Hello PDQBach,
Thank you very much for your assistance. I appreciate it very much.
I am a moderately experienced user, but I suffer from the occassional brain fart some days. Your articulate and detailed explaination has reminded me of exactly what I needed to do.
I understand exactly what...
I need to be able to assign a resource 2 hours work, but allow him a duration of 3 days to complete the task in the project.
This way I can still track the actual work hours assigned, versus the duration of the task. Any help is appreciated.