Julie
The magic sentence is:
Effort-driven only comes in to play when adding or subtracting named resource.
Thank you very much.
I think I will gain big use from you and this forum.
Fakhri
Dear all
The following is the definition in Program help of effort driven:
When a task is effort driven, Microsoft Office Project keeps the total task work at its current value, regardless of how many resources are assigned to the task.
When new resources are assigned, remaining work is...
Dear Julie
Thank you for response.
I am sorry I missed to mention that,:
1- case 1 is not effort driven.
2- case 2 is fixed work.
Case 1
You are right. You agree with me about the task behavior. This behavior is not as mentioned in program help. This is my case.
Case 2
It is a fixed work...
Task types in MS Project 2007 does not act as in program help.
Case one:
For a fixed units task of 4 days duration and 8 hours/day using only one work resource R1 at 50% units to perform work of 16 hours, if I add a work resource R2 to this task at 50% units, program recalculates work to 32...