Hi,
I've added assignment units as a new field as yyou suggested but for some reason it shows up blank even though next to the resource name it shows Matt[15%] for example.
If you were to double click on the task in resource view it brings up task information view and it shows the 15% there...
HI
In the resource name field I have Persons name [%15](you can edit if you double click on the person and go into the Task information then go to units which is set units. Is it possible to display those units in another column instead of the same column as resource names? I've tried to add...