Hello all,
In my MSP % complete situation from yesterday, 11-04, i had 63% complete.
When i change the actual date for 12-04, today´s situation.
-Project>Project Information> Status Date: 12-04-2011
The %complete automatically turns 66%...
And after it, if i turn,
-Tools>Tracking>Update...
Procygnus,
4. I have this option in use. Should i?
Answering your questions:
5. I´m using the option " Set 0%-100% complete".
7. In english i don´t know exactly the translation of this indicator, anyway, below i show the formula:
IPF – Índice Progresso Físico (portuguese)
= % complete...
Hello!
Thanks for helping..
I send the project plan, as you ask (procygnus).
As you can see the total "% Work Complete" in this project is 71%!
But the only way, for me to get it, was to assign manually each % for every tasks. I would like to have it automatically!
I tried these...
Hi everyone!
I would like to ask 2 things.
-First of all, what´s the main difference between %complete and %work complete?
-Second of all, in my Update Project, when I insert the column "%complete" the tasks wich didn´t start yet, comparing with the date i put in the.... Project>Project...