Ok, first, let me thank you all for your efforts so far. I appreciate it.
"To begin: don't add "[20%}" - let Project calculate that."
Somewhere I have to tell project that my resource is going to spend about 1.5 hours each day to the project. I don't know how else to do this.
Then, I want...
Ok, I realize I can change the loading for April. But now, same situation, and my resource's task shifts from April to the last week of March through the 3rd week of April. Same work, but one week sooner. Let's call this work task A.
Now, if I have changed April's resource calendar, my Gantt...
Sorry if this is covered elsewhere, I don't even know what to search on.
So, I have a resource who is working 20% of his time on some task. because of the way things work out, this is for the entire month of April.
So, for this task, I added a [20%] behind his name in the Gantt chart resource...