Thanks a lot @procygnus.
I have revised the work again reducing the tasks and incorporating your corrections but this time there is no red line at all.
Kindly view the attached and tell me what might be wrong.
http://www.mediafire.com/?0832dujoxkeyxes...
Thanks @procygnus, I did just what u told me, I removed the constraint (set the beginning task to as soon as possible) still not gettin any result the red line starts from a date in April 2011 while the project start date was designed for November 2010.
Please can any MS project 2007 expert helpme wit this?
My project critical path is refusing to start from the beginning of the project instead it is starting at a later date.Please help as I need to hand in the plan by Thursday 31-03-2011.
Thanks.