Thanks e1 & ponderworks, I appreciate your input. I actually figured it out after more investigation. The client was wanting a milestone update in MS project however I refused to send the entire plan to them with all my actuals and cost tables. Therefore, I use the save as feature to extract...
I have been saving out my plan as an mdb as it allows me to export only the lines I want the client to see, without any resource or actuals information. The problem I am having is that some of the dates actually change. I have checked the project start date under project information(no impact)...