Hi all
I’m having a strange problem that I hope someone can help me with.
In my plan (MS project2010), the working time per day is set to 7 hours and working week is 35h.
I create a task with Work 16 hours and assign it to one (1!) resource working 100% (=7 hours a day). MS Project, in Gantt...