  1. stct

    Baseline1 Estimated finish v/s Baseline1 Finish date - data disconnect.

    Greetings! We are on MSProject 2010 Professional - version 14.0.7015.1000 (32 bit). Noted following issue while exporting MS Project Task data (through Map and save as excel 97-2003 type. When exporting Baseline1 Estimated Finish date field, it has a different value exported intoexcel, than...
  2. stct

    Baseline1 estimated finish - export to excel - data disconnect. - MSProject 2010 SP1

    Greetings! I am a new member to this forum, and saw really good discussions in the subject area. I need some help on data disconnect after exporting into the excel format. We are finding some disconnect on the data in the field 'BaselineX Estimated Finish' - after saving the project in an...
  3. stct

    Finish Variance in Resouce Usage View

    Hi all, Is there a way we can display a Task level column in 'Resource Usage view' with following formula: Finish Variance = [ Baseline Finish Date (Task) - Finish Date (Task) ] Custom field could be an option, but did not give the correct results. I would prefer to use non-custom (stock)...
  4. stct

    Dynamic date filter in Resource Usage view

    Greetings! I am trying to define a custom filter with following condition in 'Resource' Usage view: 1. Display Not Completed tasks (i.e. %Work Complete < 100%) AND 2. Start < [Today + 15 days] OR Basline Start < [Today + 15 days] I first defined custom date fields to capture (Today + 15...
  5. stct

    Convert Microsoft Project network diagram to MS Visio flow chart

    Hi all, Is it possible to convert network diagram from MS Project into MS Visio flow chart type? I tried some of the options thro Timeline type of visio chart, but could not find the right option. Thanks in advance,