Hi,
I have 2 tasks
Task Start Finish
Task A - 01/Jul/2010 15/Jul/2010 resource 1, resource 2
Task B 28/JUn/2010 05/Jul/2010- Resorce 2
But I want resource 2 to start after he has completed tasks B i.e. after 05/Ju/2010. How do I show that in the plan, such that it does not show...