I think I've resolved this issue by changing from Fixed Units to Fixed Work as the task type. I now have another problem.
I'm seeting up a workshop which I expect to take 10.5 hours (1.5 days) of effort.
I expect the duration to be 3.5 hours (0.5 days)
I want Stephen to attend who has max...
I'm in the process of setting levels of productivity for staff so that they have time to manage ad-hoc tasks around assigned project work.
For example: Graham is available for project work 50% of the time. I've set max units to 50%.
When I set up a task in the gantt chart I specify its...