Ok so an update on this.
I found out that the Field Tech position I have was somehow scheduled for a night shift. I fixed that, but it didn't change how their work is distributed through the course of the project. I tried leveling him as well but that didn't seem to do anything.
Is there any...
JulieInMaine is my hero!
That's pretty embarrassing that I set that option off and then spent hours trying to figure out why it wasn't calculating (::blush::).
Oddly enough it still didn't calculate the actual work values until I changed the project calendar to the one all the resources were...
Ok I'm posting this anyway because I trust you guys, and this is driving me crazy.
So I'm less worried about the overallocated resources at this point, It would be nice to fix but it's not absolutely critical. It IS critical that the actual cost column calculates correctly which it is not...
Hmm yeah It's private stuff for the company, they don't want me to post it here.
I don't have any task calendars assigned. I entered the work in hours manually but didn't do anything after that. The subtasks are all manually scheduled but the summary tasks are all automatic.
Sorry, it is running on some version of Windows 7, I'm connecting remotely to the computer that uses it so I'm always confusing my systems.
It is project 2010. I don't have any elapsed duration tasks scheduled and the resource calendar is standard, no working on weekend. I'm looking at work...
Thanks for the responses!
Still can't get it to work though. First off I'm running SP3 so I don't think that bug is the issue.
Secondly I made sure all the calendars are set to none, and viewed the resource usage menu, and sure enough there are days on the weekend that are getting hours for...
Thanks Julie!
I went into the resource sheet and added the Max Units column and the Peak column. Her Max Units is set to 100% just like all my other resources, and her Peak is at 4%.
I'm really confused, She's working less than 1 hour a day spread out over a few months, I don't understand how...
Hi there,
I'm hoping you guys can help me with a very confusing problem I am having with one of my resources. I have this resource assigned to a 3 month long task, in which she only needs to work 8 hours. The program divides her time up and she's working less than half an hour a day.
But...