I am using 2007.
I have done that but on the milestones it will not shown text 2.
I think I have uploaded a sample file.http://www.mediafire.com/?mjg32y81e39l5
Can I add task name to the milestone bar to the left as the date is automatically placed to the right.
I have set up a column "Text 1" and copied the task names into it and have set the bar text up to display Text 1 to the right. Now I have made a second column "Text 2" but I can not get it to...
Thanks
You are correct I have 14 fitters (7 per shift)etc etc.
They have been assign different tasks for each shift such as working in groups of 2's and 3's.
No it is not data driver.
It is a double shift 8 week shutdown and the resources are ether on day or night shift for the duration of...
On a 2 shift project (2 x 12 hr shifts per day) what are the numbers of resources do I need to input as the "max units"
I have the following numbers per shift:
7 fitters
17 pressure welders
6 welders
10 riggers
10 labourers
Are these the correct "max units" I use or do I need to double up for...
I am trying to change the working hours on a project, I have sarted with a 24 hr calender as this project we will be working around the clock for 4 weeks.
I would like to step up the working day showing the meal breaks but I can only set up 5 periods.
Week 1 (single shift)
Start time 7:00am
1st...
Hi
Iam planning a boiler shutdown working 2 x 12 hr shifts for 14 days, can I change the format of the Start & Finish columns from Fri 19/06/09 to 8:00pm 19/06?
Thanks.