Using the Visual Reports function in Project 2007, I can create "S-Curves" using the "Earned Value Over Time" Report.
I want to show "Cumulative Cost" vs the actual cumulative cost.
"Cumulative Cost" is based on "Cost".
My actual cumulative cost would be the sum of "Actual Cost" over the time...
MS Project 2007
When printing, I can use the timescale function to adjust the time period shown.
However when in Gantt view, all tasks are still shown/printed.
How do i limit the tasks to only those that occur during the 3 week period?
thanks