Like PDQBach said, communication is very important. But the challenge is dealing with people and managing their conflict expectation. In my example, i have a sponsor who just wants the project on time versus a functional responsible who wants requisites impossible to achieve on time. Dealing...
if you are not sure how much time you need for every task, you can use the PERT Analysis. Basically you give 3 estimates for every task: optimistic, normal and pessimist.
Then take the estimates and calculate the task duration using the next formula:
DURATION = (OPTIMISTIC + 4 x NORMAL +...