  1. editoremma

    Phantom Work Allocation

    I have had a closer look at the Resource Usage sheet since my last post, and what I have noticed is that the tasks that have the Project with the defined path are from a Project that no longer exists. When I first made the project Questions Update, I spelled Questions incorrectly and i Renamed...
  2. editoremma

    Phantom Work Allocation

    Here we go, I think I have done everything you asked. You have a complete list of all the tasks and subtasks in my project file with the project column displayed. I also remembered to use PrintScreen to capture the images this time. I am not sure but I think the problem has something to do...
  3. editoremma

    Phantom Work Allocation

    Sorry, forgot to add "Project" to Resource Usage. When I added this column I discovered something interesting, that I am sure you will notice yourself, it made me aware that I have several more 'Phantom Tasks' in this project all assigned by the one project. Very weird. I have added screen...
  4. editoremma

    Phantom Work Allocation

    Thanks for the suggestion, unfortunately the 'phantom tasks' aren't in the project '2008 Tasksheet Creation' If you look down into the final image on the html page you can see the expanded version of that project, I just grabbed an image with it not expanded in the previous image. My mistake. I...
  5. editoremma

    Phantom Work Allocation

    No I am not in any hurry for this resolution, I figured it might take a while to correct. Thanks for all your help. I have attached a number of images which might help clarify the problems I am having. Image 1, PhantomTask01 shows the tasks that have been added to the resource that don't exist...
  6. editoremma

    Phantom Work Allocation

    I call it a phantom resource because but it is more of a phantom task. When I go into Resource Usage and look through the list of tasks for the resource in question there are two tasks with work allocated to the resource that does not exist in the project. I have no idea how to delete these two...
  7. editoremma

    Phantom Work Allocation

    I have a Project file that has imported a number of smaller projects. For some reason work has been allocated to a resource that is not in the project. How do I delete this 'phantom' work allocation? I am using Project 2003 Thanks in advance for any and all help.