I found the problem. Under the Task Information, the constraint was set to "As Early As Possible". When I changed this to a fixed start date, I could set the percent completion to zero without the dates shifting.
The project file I'm working on has several of the tasks entered as 100% complete, which is incorrect. If I change this to 0%, the start dates are shifted back several months (to 7/5/06). How do reset the percent complete without changing the start/end dates?
Seem to have solved my own problem, but I don't know why: I used the "Compact and Repair" utility, and now everything seems to work OK, but what is it that I 'fixed' by doing this?
- Brian
I'm trying to use the value of a control in a form to compute an auxiliary text expression within the same form, but everything I try results in "#Name?" being displayed as the result. So, I tried something even more simple: just displaying the single value itself. If I enter the...
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
By continuing to use this site, you are consenting to our use of cookies.