  1. obrian7

    Changing % complete changes the start date

    I found the problem. Under the Task Information, the constraint was set to "As Early As Possible". When I changed this to a fixed start date, I could set the percent completion to zero without the dates shifting.
  2. obrian7

    Changing % complete changes the start date

    The project file I'm working on has several of the tasks entered as 100% complete, which is incorrect. If I change this to 0%, the start dates are shifted back several months (to 7/5/06). How do reset the percent complete without changing the start/end dates?
  3. obrian7

    NewbieQ: #Name? error when using a control's value

    Seem to have solved my own problem, but I don't know why: I used the "Compact and Repair" utility, and now everything seems to work OK, but what is it that I 'fixed' by doing this? - Brian
  4. obrian7

    NewbieQ: #Name? error when using a control's value

    I'm trying to use the value of a control in a form to compute an auxiliary text expression within the same form, but everything I try results in "#Name?" being displayed as the result. So, I tried something even more simple: just displaying the single value itself. If I enter the...