Is there a way to set a new baseline where my Resource standard rates have changed, but I want to keep the original work and dates? The project has been going on for a while, actuals have been entered and now they want me to use a different rate to calculate earned value.
I have the same issue with duplicate tasks but, following the directions provided previously I now see each assignment under each project.
Developer
Project
Task
I do not use the resource pool any more except in the initial project set up. I originally thought that was the best way to...
Per your previously provided instructions I sorted the resource usage and have the info I am looking for in a decent format. Is there a way to export this to excel in this format? Do you have another suggestion to get this info out to the development managers?
Thanks you for this post! I finally finished creating all my projects, followed your instructions and got exactly what I was looking for. I did use a resource pool to set my projects up which ensured that the names were consistent. Then when I was done I switched each project to use own...
I have about 8 small to medium projects to manage on an ongoing basis. When one project completes the resources rolls onto a new one. My questiion is what is the advantage to using indivdual project plans with a shared resource pool vs. 1 plan where each project has a section. My main concern...
When I update my project with new information I input the status date (same as current date in my case) and all the corresponding task information. Often I have tasks that should have been completed by the status date which haven't even been started. Project just leaves them behind the current...