I found a way to do it. This is counter-intuitive, but it works. I check the box in the Advanced tab of Task Information that says "Scheduling ignores resource calendars". The "24 hours" calendar is chosen.
I'm using MS Project to schedule work in a lab. Some resources (people) work about 8 hours a day and about 40 hours a week. Other resources (hardware) are available 24/7. We have a lot of analyses where a chemist prepares a mix and then must let it dry (or cook or extract) for at least 12...