I appreciate your helpful comment about micro-managing but a simple answer would have been sufficient without the side comments. You should keep that in mind when providing "help" on this forum because people are looking for answers for their questions; they don't care about your personal...
Hello,
I am trying to use Task Usage and Resource Usage views to schedule individual resource assignments during the duration of the task. A task can have a total duration for many weeks, but resources (people) are typically used on-and-off during that task. To schedule this, I use task usage...
I am a very basic MS Project 2007 user and I am struggling to get an answer to my question, I hope that someone here will be kind enough to help me.
I have a single task and I would like to assign multiple resources. The task is a field assignment for our technicians and the work will be...
I am new to Microsoft Project and trying to understand how to set up a task with a "floating" duration that has a start date based on the end of one task and an end date that is based on the start date of another task. This is done to show the duration "task" between two tasks with fixed dates...