it`s not the planning phase
it`s the tracking phase
the plan is between 25.09-28.10
i edit `actual date` to 13.09 (it`s not on the planning it`s in tracking)
i edit the complete : %2
so it splits task
1) Only sunday is off
2) it has predecessor and successor.
3) i changed the actual start date to 13.09 and put %complete to 2%.. duration won`t change
so, first 7 days i`ll finish 2% of work, and next 23days i`ll finish 98%
i think that ms project is not for tracking the construction works. It...
In a construction plan, i have a task
Start : 20.09.06
Finish: 28.10.06
Duration: 30d
Resources : material 1450, work 710h
so, actually :
start: 13.09.06
complete% : 2% for 20.09.06
if i enter the values of start date and %complete, ms project splits the task`s 2% part and keeps empty...